I will explain how can you assign overtime hours and overtime Pay Rate to Resource in MS PROJECT 2010
First I will add TASK 1 with 5 days duration:
Now I will add Mary as a resource with $100/hour as standard pay rate, and $150 / hour as overtime pay rate:
Now I will assign Mary to the TASK 1:
You can see $400 in the Cost field (5 days X 8 hours/day X $100 / hour = $4.000)
Now, I will choose the Gant chart view open the Task form ad a detailed view:
I will click ANYWHERE in the Task Form and then I will click on the Format Tab, in the Details Group –> WORK:
Now I will put 16 hours in the Overtime work field. It means that Mary will work 16 hours overtime:
It seems like nothing happened in the Gant chart? I will now click anywhere in the Gantt chart portion of the screen and I will get:
You can see that TASK 1 will have only 3 days duration. Why? Well, if you add overtime work on the task the same amount of work will be done but in shorter period.
I will now close the Task form:
and I will open the Resource usage sheet:
You can see 40 hours that in the Work field. Why? Because initially TASK 1 had 5 days duration (e.g. 40 hours). By adding 16 hours as overtime, TASK 1 will not last 40+16 = 56 hours, but those 40 hours will be done in shorter period.
Why 13.33 hours/day? 40 hours of total work – 16 hours of overtime work is 24 hours. 24 hours divided by 8 hours regular work per day is 3 days. O.K. we have 3 days duration. And Mary will work 8 hours each day (regular work) and (16 hours of total overtime / 3 days) = 5.33 overtime hours per day. So, 8 + 5.33 = 13.33.
Now, I will open the Cost table:
And I will get
Why? Well, Mary will work 40 hours on the TASK 1. 24 hours is regular work, and 16 hours is overtime work. 24 X $100 (standard rate per hour) = $.2400, 16 X $150 (overtime rate per hour) = $2.400. So, the total cost fore the TASK 1 is $2.400 + $2.400 = $2.800.
Overtime work is complicated, so you should use it with caution!
quoted by
SISINDOTEK - IT Training & Solution Provider
Office 1 : Jl. Pelajar Pejuang 45 No.23 , Lt.2 Bandung - Jawa Barat
Office 2 : Jl. Sukasenang VI-6B Bandung - Jawa Barat 40124
Tel. 022-71242266, SMS. 0812.8733.1966
info , YM. sisindotek
www.sisindotek.com , facebook.com/sisindotek , twitter.com/sisindotek
Please consider your environmental responsibility.
Before printing this e-mail message, ask yourself whether you really need a hard copy.
"All information in this message and attachments is confidential and may be legally privileged. Only intended recipients are authorized to use it. E-mail transmissions are not guaranteed to be secure or error free and sender does not accept liability for such errors or omissions. The company will not accept any liability in respect of such communication that violates our e-Mail Policy."
First I will add TASK 1 with 5 days duration:
Now I will add Mary as a resource with $100/hour as standard pay rate, and $150 / hour as overtime pay rate:
Now I will assign Mary to the TASK 1:
You can see $400 in the Cost field (5 days X 8 hours/day X $100 / hour = $4.000)
Now, I will choose the Gant chart view open the Task form ad a detailed view:
I will click ANYWHERE in the Task Form and then I will click on the Format Tab, in the Details Group –> WORK:
Now I will put 16 hours in the Overtime work field. It means that Mary will work 16 hours overtime:
It seems like nothing happened in the Gant chart? I will now click anywhere in the Gantt chart portion of the screen and I will get:
You can see that TASK 1 will have only 3 days duration. Why? Well, if you add overtime work on the task the same amount of work will be done but in shorter period.
I will now close the Task form:
and I will open the Resource usage sheet:
You can see 40 hours that in the Work field. Why? Because initially TASK 1 had 5 days duration (e.g. 40 hours). By adding 16 hours as overtime, TASK 1 will not last 40+16 = 56 hours, but those 40 hours will be done in shorter period.
Why 13.33 hours/day? 40 hours of total work – 16 hours of overtime work is 24 hours. 24 hours divided by 8 hours regular work per day is 3 days. O.K. we have 3 days duration. And Mary will work 8 hours each day (regular work) and (16 hours of total overtime / 3 days) = 5.33 overtime hours per day. So, 8 + 5.33 = 13.33.
Now, I will open the Cost table:
And I will get
Why? Well, Mary will work 40 hours on the TASK 1. 24 hours is regular work, and 16 hours is overtime work. 24 X $100 (standard rate per hour) = $.2400, 16 X $150 (overtime rate per hour) = $2.400. So, the total cost fore the TASK 1 is $2.400 + $2.400 = $2.800.
Overtime work is complicated, so you should use it with caution!
quoted by
SISINDOTEK - IT Training & Solution Provider
Office 1 : Jl. Pelajar Pejuang 45 No.23 , Lt.2 Bandung - Jawa Barat
Office 2 : Jl. Sukasenang VI-6B Bandung - Jawa Barat 40124
Tel. 022-71242266, SMS. 0812.8733.1966
info , YM. sisindotek
www.sisindotek.com , facebook.com/sisindotek , twitter.com/sisindotek
Please consider your environmental responsibility.
Before printing this e-mail message, ask yourself whether you really need a hard copy.
"All information in this message and attachments is confidential and may be legally privileged. Only intended recipients are authorized to use it. E-mail transmissions are not guaranteed to be secure or error free and sender does not accept liability for such errors or omissions. The company will not accept any liability in respect of such communication that violates our e-Mail Policy."
Comments
Post a Comment
Silahkan isi komentar atau iklan baris Anda, Jangan lupa visit social media kami di FB/Twitter/Instagram @alamatclick